Reconciled from Infrastructure Canada · 44% match confidence
Major capacity and treatment upgrades to Canada's largest wastewater treatment plant serving 1.6 million people.
Federal match flagged: confidence 0.43
Original Approved(2020)
$3.4B
Current Approved(2024)
$4.2B
Budget Variance?The change between a project's originally approved budget and its current approved budget. Positive numbers mean the budget grew (over original); negative means it shrank. Only projects with multi-year history can show a variance.· 3 cycles
$800.0M(+23.5% over original)
Original Target
—
Now Expected
Aug 2009
Schedule Slippage
—
Original (2020)
$3.4B
Current (2024)
$4.2B
Jan 1, 2020
Original budget approved
$3.4B
Jan 1, 2022
Budget revised
+$400.0M (+11.8%)
Jan 1, 2024
Budget revised
+$400.0M (+10.5%)
Apr 2, 2026
Project tracked
Added to CivicLedger
Sources matched
9
Match confidence
44%
Low confidence
Latest ingestion
Apr 2, 2026
Infrastructure Canada
Record #6953 · Refreshed Apr 2, 2026
48%
confidence
Infrastructure Canada
Record #7633 · Refreshed Apr 2, 2026
45%
confidence
Infrastructure Canada
Record #7381 · Refreshed Apr 2, 2026
45%
confidence
Infrastructure Canada
Record #6734 · Refreshed Apr 2, 2026
44%
confidence
Infrastructure Canada
Record #6665 · Refreshed Apr 2, 2026
43%
confidence
Infrastructure Canada
Record #7630 · Refreshed Apr 2, 2026
43%
confidence
Infrastructure Canada
Record #7429 · Refreshed Apr 2, 2026
43%
confidence
Infrastructure Canada
Record #7359 · Refreshed Apr 2, 2026
42%
confidence
Infrastructure Canada
Record #6788 · Refreshed Apr 2, 2026
40%
confidence
Project record last updated: 4/2/2026