Jun 30, 2011
·Metrolinx Master Agreement, 2011
Initial budget approved$5.3B
Original capital cost approved at $5.3B for the 19 km Eglinton Crosstown light rail line, with Metrolinx as the proponent and a target opening of 2020.
Read the source →Reconciled from Toronto Capital Budget · 100% match confidence
Original Approved
$430K
Current Approved
$430K
Budget Variance?The change between a project's originally approved budget and its current approved budget. Positive numbers mean the budget grew (over original); negative means it shrank. Only projects with multi-year history can show a variance.
$0(0.0% on original)
Original (2025)
$430K
Current (2025)
$430K
Jun 30, 2011
·Metrolinx Master Agreement, 2011
Original capital cost approved at $5.3B for the 19 km Eglinton Crosstown light rail line, with Metrolinx as the proponent and a target opening of 2020.
Read the source →Dec 15, 2021
·Metrolinx Board, December 2021
Opening pushed from 2022 to 2023 after Crosslinx contractor reported integration and testing delays on the underground stations. Provincial transit agency acknowledged delivery date had slipped a second time.
Read the source →Sources matched
1
Match confidence
100%
High confidence
Latest ingestion
Apr 2, 2026
Toronto Capital Budget
Record #23799 · Refreshed Apr 2, 2026
100%
confidence
Project record last updated: 4/27/2026