Reconciled from Toronto Infrastructure · 62% match confidence
Expansion of protected cycling infrastructure along Bloor Street from Shaw to Runnymede and east of Avenue Road.
Infrastructure match flagged: confidence 0.62
Original Approved(2020)
$45.0M
Current Approved(2024)
$58.0M
Budget Variance?The change between a project's originally approved budget and its current approved budget. Positive numbers mean the budget grew (over original); negative means it shrank. Only projects with multi-year history can show a variance.· 3 cycles
$13.0M(+28.9% over original)
Original (2020)
$45.0M
Current (2024)
$58.0M
Jan 1, 2020
Original budget approved
$45.0M
Jan 1, 2022
Budget revised
+$7.0M (+15.6%)
Jan 1, 2024
Budget revised
+$6.0M (+11.5%)
Apr 2, 2026
Project tracked
Added to CivicLedger
Sources matched
1
Match confidence
62%
Low confidence
Latest ingestion
Apr 2, 2026
Toronto Infrastructure
Record #10 · Refreshed Apr 2, 2026
62%
confidence
Project record last updated: 4/2/2026