Reconciled from Toronto Capital Budget · 82% match confidence
Construction of new GO Transit stations along existing rail corridors to provide subway-like service within Toronto.
Evolved from Mayor Tory's SmartTrack proposal. Five stations confirmed. Integrated with Metrolinx GO Expansion.
Original Approved(2020)
$1.5B
Current Approved(2025)
$379.8M
Budget Variance?The change between a project's originally approved budget and its current approved budget. Positive numbers mean the budget grew (over original); negative means it shrank. Only projects with multi-year history can show a variance.· 4 cycles
$1.1B(-74.0% under original)
Original (2020)
$1.5B
Current (2025)
$379.8M
Jan 1, 2020
Original budget approved
$1.5B
Jan 1, 2022
Budget revised
+$200.0M (+13.7%)
Jan 1, 2024
Budget revised
+$140.0M (+8.4%)
Dec 31, 2025
Budget revised
$1.4B (-78.9%)
Apr 2, 2026
Project tracked
Added to CivicLedger
Sources matched
1
Match confidence
82%
Moderate confidence
Latest ingestion
Apr 2, 2026
Toronto Capital Budget
Record #29683 · Refreshed Apr 2, 2026
82%
confidence
Project record last updated: 4/2/2026