George Street Revitalization
Under Construction
CommunityWard Toronto CentreConstruction of an integrated health and social services hub at 251 George Street including emergency shelter, transitional housing, and health services.
Replaces Seaton House men's shelter. Will be North America's largest purpose-built shelter and services hub.
Original Approved
$325.0M
Current Approved
$360.0M
Budget Variance
$35.0M(+10.8%)
Budget Timeline
Project History
Jan 1, 2020
Original budget approved
$325.0M
Jan 1, 2022
Budget revised
+$55.0M (+15.3%)
Jan 1, 2024
Budget revised
+$55.0M (+13.3%)
Apr 2, 2026
Project tracked
Added to CivicLedger