Jan 1, 2022
Initial budget approved$1.2B
Initial approved budget
seed
Planned streetcar extension along Queens Quay East to serve the East Bayfront, Villiers Island, and Port Lands communities.
Critical transit link for the Port Lands development. Environmental assessment approved. Awaiting full funding commitment.
Original Approved(2022)
$1.2B
Current Approved(2024)
$1.4B
Budget Variance?The change between a project's originally approved budget and its current approved budget. Positive numbers mean the budget grew (over original); negative means it shrank. Only projects with multi-year history can show a variance.· 2 cycles
$150.0M(+12.5% over original)
Original (2022)
$1.2B
Current (2024)
$1.4B
Jan 1, 2022
Initial approved budget
seed
Jan 1, 2024
seed
No linked sources yet. Sources are matched automatically during data ingestion.
Project record last updated: 4/2/2026