Expansion and upgrade of Highland Creek wastewater treatment facility in Scarborough to increase capacity.
Required to accommodate population growth in Scarborough. Environmental assessment underway.
Original Approved(2022)
$850.0M
Current Approved(2024)
$920.0M
Budget Variance?The change between a project's originally approved budget and its current approved budget. Positive numbers mean the budget grew (over original); negative means it shrank. Only projects with multi-year history can show a variance.· 2 cycles
$70.0M(+8.2% over original)
Original (2022)
$850.0M
Current (2024)
$920.0M
Jan 1, 2022
Original budget approved
$850.0M
Jan 1, 2024
Budget revised
+$70.0M (+8.2%)
Apr 2, 2026
Project tracked
Added to CivicLedger
No linked sources yet. Sources are matched automatically during data ingestion.
Project record last updated: 4/2/2026